Reiter focus group meeting August 25th 2010

nowires

Well-Known Member
Joined
Jul 20, 2008
Messages
3,669
Reaction score
0
Location
Baring
Just thought I would bring this up that once a month we all meet in Everett and talk and discus what is happening at Reiter. DNR is getting close to releasing the final sepa and it would be a great time to show our support and have the 4x4 community show up in force

Time: 7 to 8 9 p.m.
Place: Public Meeting Room #2
 
Last edited:
your link for driving directions didnt work...but i will be there havent wheeled at reiter but i am always ready to support the 4x4 community
 
It was a good meeting
It looks like the trail designs will be out by the end of September and the SEPA will start in November sometime
 
:awesomework: I was alittle busy loading 2.5 cords of wood onto the trailer tonight. Gotta have it unloaded/stacked by sat am, so I can go get another 2 cord...:yikes:
 
Oopps.....forgot about this. I actually did want to go.

It looks like the trail designs will be out by the end of September and the SEPA will start in November sometime

Um....."out" meaning their job is complete and we have a trail design? Or "out" meaning they will be replaced?

The SEPA will start because the trail design is complete, correct?

A little clarification would be nice.:awesomework:
 
Um....."out" meaning their job is complete and we have a trail design? Or "out" meaning they will be replaced?

The SEPA will start because the trail design is complete, correct?

A little clarification would be nice.:awesomework:

Out as in the trails will be on paper that we are going to keep. Right now all trails are going through a review process and some night change or be eliminated do to one cerconstance or another

I guess YES to your first questian
 
:awesomework: I was alittle busy loading 2.5 cords of wood onto the trailer tonight. Gotta have it unloaded/stacked by sat am, so I can go get another 2 cord...:yikes:

I will put that one in the excuse book also as a way out of something
 
I will share what I took away from the meeting.




Here are the items that DNR had charted out for their work schedule:

1. Overall Trail Layout
2. Trail Design for Phase 1- Outside of Critical Areas
3. Prepare SEPA & Permit Info
4. SEPA Review & Public Comment
5. SEPA Review & Final Determination
6. Obtain Permits & Approvals
7. Contracts- (Some work may be contracted out)
8. Construction Phase 1
9. Open Phase 1
10. Phase 2- Requiring Conditional Use Permits, HPA
 
I will put that one in the excuse book also as a way out of something

How about talking about what was discussed at the meeting instead of taking pokes at those who couldn't. :awesomework:


I thought you were more of a leader and bigger than that. :kiss:
 
Jesus Neil, you sound like a little kid, Grow up :rolleyes: You have to learn when to quit while you're behind...
---As for him poking me, I am plenty grown up to figure out that Charlie was just ribbing me for fun, and he knows that I have alot of obligations and things I needed to get done around the house I put off to be able to work on the reroute at walker for 2 weekends in a row---
---I have told Charlie I intend to attend some Focus group meetings when I can. There will be plenty more in the coming months/yrs. Until then, I will find out what I need to find out to stay informed without belittling anyone.
 