Wow no wonder nothing gets doneHere is some production numbersIf we build roads a road 10ft wide with 1 ft of rock is .37 yds of material per ftOr 1 yd of material per 3 ft of roadA track dump can haul 8 yds of material or 27 ft of road per loadAt a load interval of 1 load every 5 minutes or 320 ft per hour or 2560 ft per dayWith delays in trucking of material to the job site and breakdowns I figure 2 miles a weekSo on my math that is 4 weeks for 8 miles of baseBut all of the trail doesn
Wow no wonder nothing gets done
Here is some production numbers
If we build roads a road 10ft wide with 1 ft of rock is .37 yds of material per ft
Or 1 yd of material per 3 ft of road
A track dump can haul 8 yds of material or 27 ft of road per load
At a load interval of 1 load every 5 minutes or 320 ft per hour or 2560 ft per day
With delays in trucking of material to the job site and breakdowns I figure 2 miles a week
So on my math that is 4 weeks for 8 miles of base
But all of the trail doesn